5-month road project starts June 5 on Chiwawa Loop

Chelan County Public Works reminds residents that work begins Monday, June 5, on the Chiwawa Loop Phase III road reconstruction project.

Motorists can expect to see minor traffic delays the first week of construction, as Reece Construction Co. will be installing construction traffic control signs along the project area. The following week (June 12), the contractor will commence clearing and grubbing from Sumac Lane to Wending Lane, which will require one-lane flagging with up to 20-minute delays.

The project, which will take about 85 working days, includes reconstructing the roadway from Wending Lane to Sumac Lane (mp 3.35-mp 4.57). In addition to a new roadway base and surfacing, the project will also widen the road from 22 to 30 feet, improve drainage and roadway geometrics, and install guardrail.

Contracted crews will begin at Sumac Lane and work their way back to Wending Lane. Most weeks, crews will be working 7 a.m. to 6 p.m. Monday through Thursday. The contractor may be working some Fridays as the project progresses.

At this time, a five-day detour is planned for July 24-28 so that crews can install a box culvert. Those dates will be confirmed as the project gets underway. The detour will be via Beaver Valley Road and Highway 207.

On May 30, Chelan County commissioners approved a temporary speed limit reduction on Chiwawa Loop Road in the project area. The speed limit reduction is necessary because during construction roadway widths may be temporarily reduced or lanes may be temporarily closed. Beginning June 1, the speed limit will be reduced to 25 miles an hour until such time that construction is substantially complete.

Other impacts to motorists and homeowners:

  • The road will be down to one lane during the day, with flaggers and pilot cars controlling traffic.
  • Motorists should plan for up to 20-minute delays at times.
  • Access to properties will be maintained. This includes access for mail delivery, garbage pickup, etc. If a driveway will be impacted, Reece Construction will contact that property owner directly.

Watch the Chelan County Public Works Facebook page for updates.

Last Updated: 08/24/2021 09:04 AM

Chelan County Calendar

Upcoming events and schedules at the county!

  • 22
    May 2024
    06:30 PM - 08:00 PM

    Planning Commission - May 22, 2024

    Posted by: Community Development

    400 Douglas Street
  • 15
    May 2024
    07:00 PM - 08:00 PM

    Assessor's Office Community Meeting: Leavenworth and Lake Wenatchee

    Posted by: Chelan County Assessor

    Chelan County Assessor Wes Cornelius invites property owners and all interested parties to attend one of four community meetings scheduled this spring throughout the county.

    Chelan County Fire District 3 station
  • 13
    May 2024
    08:00 AM - 05:00 PM

    Final day to withdraw from the ballot

    Posted by: Chelan County Elections

    Final day to withdraw from the ballot

  • 10
    May 2024
    05:00 PM - 05:30 PM

    Lot Drawing for Candidates

    Posted by: Chelan County Elections

    Lot drawing for candidates placement on the ballot.

    Chelan County Elections Office
  • 08
    May 2024
    10:00 AM - 12:00 PM

    Chelan County Civil Service Commission

    Posted by: Human Resources

    The Chelan County Civil Service Commission will be meeting on May 8, 2024.

    Chelan County Commissioners Office, ES Conference Room.