Roads identified for 2019 chip sealing season

The Chelan County 2019 Road Preservation Program has kicked off for the season, with pre-level work expected to begin the week of May 20.

Road district crews throughout the county have been crack sealing roads scheduled for chip sealing this summer. Roads in the 2019 program were previously identified based on a rating system that defines what state the pavement is in and what fix is required.

The preservation program’s progress is highly dependent on weather, equipment and, most recently, wildfire season. Roads scheduled for preservation this year are:

 

DISTRICT

ROAD

BMP-EMP

Wenatchee

 

 

 

Stemilt Creek Road

0-2.15

 

Joe Miller Road

0-2.15

 

Luebber Lane

0-0.62

 

Stemilt Hill Road

2.95-5.63

Cashmere

 

 

 

Patrick Lane

0-0.8

 

Harnden Road

0-0.44

 

Regan Road

0-0.16

 

Hinman Drive

0-0.5

 

Mt. Stuart Drive

0.17-0.36

 

Eels Road

0-1.22

 

Warner Canyon Rd

0-0.05

 

Mission Creek Road

1.51-2.59, 4.74-7.99

 

Goodwin Road

0-0.165

 

Larson Street/Ruby Street

0-0.18

 

Hughes Street

0-0.04

 

Sullivan Street

0.13-0.25

 

Turkey Shoot Road

0-0.75

 

Binder Road

0-0.1

Leavenworth

 

 

 

Chiwawa Loop Road

4.58-8.63

Chelan

 

 

 

Summit Blvd

0-0.57

 

Washington Street

0-2.29

 

Green Avenue

0-3.84

 

Upper Joe Creek Road

0-1

 

Klate Road

0-0.88

 

Manson Blvd

3.21-3.63

*BMP means beginning milepost. EMP means ending milepost.

 

 

Chelan County Public Works reminds citizens that if they live on a road slated for chip sealing that they will likely see crews in front of their home more than once during the summer road construction season. That’s because there are three steps to the preservation process: crack sealing, pre-level work and chip sealing. So crews will be moving throughout the districts while completing pre-level work and then will return for chip sealing.

Motorists should expect travel delays during both the pre-level and chip-sealing processes. Expect to see one-lane, flagger-controlled traffic with up to 20-minute delays at times. Motorists are advised to find alternate routes when crews are in their area.

For more information, visit the Pavement Preservation Program page on the county’s website. Keep up on the crew’s progress throughout the summer – and which district they are in – by following the Chelan County Public Works Facebook page.

Last Updated: 08/24/2021 09:04 AM

Chelan County Calendar

Upcoming events and schedules at the county!

  • 03
    Feb 2025
    09:00 AM - 05:00 PM

    Registration deadline for new voters or address updates by mail, online, email or over the phone.

    Posted by: Chelan County Elections

    Registration deadline for new voters or address updates by mail, online, email or over the phone.

  • 01
    Feb 2025
    09:00 AM - 04:00 PM

    Monthly Drop-Off Saturday - Feb. 1, 2025

    Posted by: Solid Waste Management

    Drop-off Saturday at the Moderate Risk Waste Facility is Feb. 1.

    Chelan County Moderate Risk Waste Facility
  • 23
    Jan 2025
    10:00 AM - 11:00 AM

    Public Meeting: Official Logic and Accuracy Test of Voting System and Accessible Voting Unit (AVU) Demonstration

    Posted by: Chelan County Elections

    Chelan County Auditor’s Office
  • 22
    Jan 2025
    01:00 PM - 03:00 PM

    Hearing Examiner - January 22, 2025

    Posted by: Community Development

    By Zoom Video Conference or in person at 400 Douglas St.
  • 21
    Jan 2025
    08:00 AM - 05:00 PM

    Ballots will be mailed to voters

    Posted by: Chelan County Elections

    Ballots will be mailed to voters