Weekly Road Maintenance Update

Road Construction & Maintenance Update: Week of Aug. 10

To minimize potential exposure to COVID-19 to staff and the public, Chelan County Public Works is open by appointment only. Call 667-6415 for an appointment.

 

County Construction

West Cashmere Bridge Replacement Project: In-water work is underway on the project and will be through Sept. 30. The construction crew will be working five days a week, building a 300-foot work trestle over the water. Recreationists on the Wenatchee River who must pass by the bridge should pass just left of the bridge’s center pier. The change in passage is temporary. This route will take river recreationists under the temporary work trestle that is being built, through a 48-foot clear area. Avoid the area where crews are working from a floating platform. More details, including a photo showing where rafters can pass, are on the project’s construction page.

 

2020 Preservation Program: Chip sealing wraps up this week in the Wenatchee area, with crews expected to be in the Sunnyslope area (Northridge Drive, Knowles Road, Rolling Hills Lane, Elizabeth Court, School Street and West Peters Street) early in the week and on Easy Street after Monday. When crews are chip sealing, the roadway is at one lane, with flaggers controlling traffic. A pilot car may be used in high trafficked areas. Minor traffic delays should be expected. Motorists are reminded not to park along the roads that are scheduled for chip sealing for the week crews will be in that area. Follow the progress of chip sealing on the CCPW Facebook page.

 

Wenatchee Heights Road Improvement Project: Project begins Aug. 10 and should be completed in mid-October. During construction, motorists should plan for some traffic delays, with flaggers directing the one-lane traffic. A pilot car also will be used to safely guide motorists through the work zone, and the speed limit in the construction area will be reduced to 25 mph.

 

Guardrail Repairs: A contractor for the county will be replacing damaged guardrail around Chelan County beginning on Aug. 10. The contractor will begin in Wenatchee, working on portions of Mission Ridge and Squilchuck roads. That work should take about two weeks. The crew then will move to Stine Hill in Cashmere, Chumstick Highway in Leavenworth and Gill Creek Road near Stevens Pass. When working, traffic is at one lane in the work area, with flaggers directing motorists. Minor traffic delays may occur. Guardrail work is expected to take about 12 working days.

 

 

Road District Maintenance

Visit the Chelan County Public Works website, where the weekly road maintenance information is regularly updated.

District 1 (Wenatchee)

Crews will be chip sealing and brooming (see above) in the Wenatchee District.

District 2 (Cashmere)

The crew will be working with the chip sealing team.

District 3 (Leavenworth)

The crew will be working with the chip sealing team. In the Leavenworth District, the crew will be brushing upper routes, hand patching potholes and prepping for upcoming skip patching.

District 4 (Entiat)

The crew will be working with the chip sealing team.

District 5 (Chelan)

The crew will be doing shoulder stabilization work in the Manson area. In the work area, motorists should expect one-lane, flagger-controlled traffic with minor delays. Crews also will be hand patching potholes in the Manson area, spot brooming recently chip-sealed roads and ditching on Stayman Flats Road.

On Aug. 12, the Traffic Safety crew will be in downtown Manson, painting parking stalls and crosswalks as well as the road’s fog and center lines. No overnight parking will be allowed on Wednesday on Wapato Way/Manson Boulevard, from Wapato Point Parkway to Wapato Way. Vehicles must be off the road by 6 p.m.

 

Last Updated: 08/06/2020 04:02 PM

Share This Page...

Chelan County Calendar

Upcoming events and schedules at the county!

  • 12
    Sep 2020
    09:00 AM - 01:00 PM

    September Parenting Class - English and Spanish

    Posted by: Superior Court Clerk

    Supporting Children Through Divorce is a four-hour educational program designed to help parents focus on the needs of their children during and after divorce and separation.

    Washington State University Extension
  • 08
    Sep 2020
    06:30 PM - 08:00 PM

    Chelan County Noxious Weed Board Meeting - 3rd Quarter

    Posted by: Noxious Weed Control Board

    Chelan County Noxious Weed Board Meeting

    Noxious Weed Conference Room
  • 02
    Sep 2020
    09:00 AM - 03:00 PM

    Hearing Examiner - September 2, 2020

    Posted by: Community Development

    Chelan County Administrative Building
  • 26
    Aug 2020
    07:00 PM - 09:00 PM

    Planning Commission - August 26, 2020

    Posted by: Community Development

    400 Douglas Street
  • 19
    Aug 2020
    01:00 PM - 03:00 PM

    Hearing Examiner - August 19, 2020

    Posted by: Community Development

    Chelan County Administrative Building