2021 shaping up to be a busy construction year
Posted On: April 05, 2021
(Photo above: This summer, a bridge will be built on South Lakeshore Road at Slide Ridge to better convey the debris, mud and rock that frequently comes off of the slide-prone area during heavy rainstorms.)
The year is shaping up to be an active construction year for Chelan County Public Works. We are headed into the second year of the largest construction project Chelan County government has ever seen (that’s the new $25.5 million West Cashmere Bridge) and this summer marks the start of a unique flood mitigation project on Lake Chelan. Add our annual chip sealing program on top of our planned projects, and you’ve got the makings for a busy construction year.
Here are some standout county projects that will impact traffic this summer:
West Cashmere Bridge Replacement Project in Cashmere: Construction on both sides of the project is in full swing. On the south side of the project at Goodwin Road, the contractor is building the fourth and final pier that will make up the substructure of the future bridge. On the north side at Hay Canyon road, the contractor is building a roundabout that will create a five-legged intersection that allows for continuous movement there. This May, watch for the large, steel girders to be set, and with that will come a few weeks of travel impacts on Highway 2 in the project area, including lane changes and speed reductions. The new bridge is slated to be open by end of year.
Slide Ridge Retrofit Project at Lake Chelan: Construction begins this summer on a single-span bridge that will be built on South Lakeshore Road at the site of Slide Ridge. The 108-foot long bridge will replace two large culverts that at times have been blocked with debris, mud and rock that was violently discharged from Slide Ridge following rainstorms. During construction a detour route will be established around the construction site on the unpaved, one-lane bypass lane that currently runs adjacent to Slide ridge. An unmanned traffic light may be used to direct traffic. Construction should take about six months.
Mission Creek Road Improvement Project in Cashmere: Construction begins in July on a 2.42-mile stretch of Mission Creek Road. The project starts near Coates Road and goes to milepost 5. The project will not only rehabilitate the roadway but also replace deficient guardrail and existing road signage and institute other safety improvements. During construction, the road will be at one lane, with flaggers and a pilot car directing traffic. There will be road delays, so best to avoid the road during construction unless you live on it.
Countywide Signing and Terminal Barrier Improvements: These road safety projects involve installing curve warning signs on portions of Manson Boulevard and South Lakeshore, Wapato Lake, Boyd and Entiat River roads. The county also will upgrade guardrail and concrete barrier terminals on portions of the Malaga-Alcoa Highway, Wenatchee Heights Road, Chumstick Highway, Boyd Road and Manson Boulevard. Traffic impacts at times may include flagger-directed traffic and minor traffic delays in the work areas.
Antoine Creek Culvert Replacement in Chelan: A contractor will upsize three culverts that run adjacent to Antoine Creek Road. The new, larger box culverts will allow for increased water flows and for debris to pass during larger runoff events, minimizing post-wildfire flooding frequency. Construction begins this spring and will take 15 working days. During construction, motorists will see flagger-controlled traffic. During nonworking hours, a detour will route traffic around the work area.
Countywide Pavement Preservation Program: The chip-sealing season in Chelan County typically starts before Memorial Day and ends just after Labor Day. It usually takes less than one day per road; however, the process includes crack sealing, pre-leveling and chip sealing. So if your county road is on the list to be chip sealed, you will see crews on your road multiple times this season. Motorists should expect travel delays during both the pre-level and chip-sealing processes. Expect to see one-lane, flagger-controlled traffic with up to 20-minute delays. For a list of the roads scheduled for chip sealing this year, visit our Pavement Preservation Program webpage.
Need more information?
Sign up to receive project updates, including construction start dates, on our listserv.
Visit our Capital Projects page for a list of our ongoing projects.
Or watch our Facebook page for updates.
Older Articles
Road crews hit the road with COVID precautions in place
Posted On: June 04, 2020
Chelan County road crews are back on the road in full force after more than two months of working with reduced crew sizes during the governor’s Stay H...
Read More arrow_forwardHeaded to the MRWF? Secure that load for safe travels!
Posted On: December 11, 2019
The new Chelan County Moderate Risk Waste Facility is open to the public. The facility is at 3612 Highway 97A in Wenatchee....
Read More arrow_forwardCode of the West: A reminder that life is different in the country
Posted On: September 06, 2019
The Code of the West was adopted in 2002 by Chelan County commissioners. It is not a formal code, but rather a philosophy or friendly advice for peopl...
Read More arrow_forwardIt's always wise to stay off the (wet) lines
Posted On: June 18, 2019
Roadway striping plays a valuable role in efforts to keep travelers safe on the roadway. The Traffic Safety crew of Chelan County Public Works re-stri...
Read More arrow_forwardIn an emergency, don't let your address delay help from reaching you
Posted On: January 15, 2019
Have you ever asked yourself the question: When seconds count, how easily will emergency responders be able to find my home? Learn how your address ma...
Read More arrow_forwardWinter is coming -- it's time to remove any vehicles parked along the roadside
Posted On: November 08, 2018
With Chelan County Public Works now preparing for winter and the inevitable snowfall that will come with it, our road crews are asking residents to re...
Read More arrow_forwardPreserving a piece of Cashmere's history
Posted On: October 22, 2018
Those people interested in giving the West Cashmere Bridge a new home -- and preserving its history -- have until Jan. 1, 2019, to contact Chelan Coun...
Read More arrow_forwardNeed wood chips? Pick them up at the Chelan Transfer Station
Posted On: September 07, 2018
Free shredded wood chips are available at the Chelan Transfer Station until about early October....
Read More arrow_forwardCounty to build year-round moderate risk waste facility
Posted On: September 07, 2018
Chelan County is in the process of opening a facility – called a moderate risk waste facility – that will be open year round to residents in need of s...
Read More arrow_forward2018 road preservation project revs up
Posted On: May 03, 2018
The 2018 Road Preservation Program is underway throughout Chelan County. Read about the list of roadways in the preservation program this year....